Timeline

Milestone Date
Statement of Interest Submitted to MSBA May 2014 and again April 2015
The Massachusetts School Building Authority (MSBA) decision to invite Arlington High School (AHS) into the School Building Grant Program January 27, 2016
MSBA Invites AHS to commence Eligibility Period May 25, 2016
Eligibility Period June 8, 2016 through March 7, 2017
AHS Building Committee Formed September 2016
Feasibility Phase (anticipated to last 16-20 months)

  • Forming the Project Team
  • Owner’s Project Manager Selected
  • Designer Selection
  • Conduct Feasibility Study
Began February 2017

  • OPM approved July 2017
  • Designer selected Oct. 2017
  • Feasibility study began Nov. 2017
Schematic Design TBD
Funding the Project TBD
Detailed Design TBD
Anticipated Completion Between 2022 and 2024