Timeline

Milestone Date
Statement of Interest Submitted to MSBA May 2014 and again April 2015
The Massachusetts School Building Authority (MSBA) decision to invite Arlington High School (AHS) into the School Building Grant Program January 27, 2016
MSBA Invites AHS to commence Eligibility Period May 25, 2016
Arlington voters approve $2M Debt Exclusion to pay for Feasibility Study June 2016
Eligibility Period June 8, 2016 through March 7, 2017
AHS Building Committee Formed September 2016
Feasibility Phase Begins (anticipated to last 16-20 months) February 2017
Owner’s Project Manager Selected July 2017
Designer Selected (HMFH Architects) October 2017
Feasibility Study Begins November 2017
Educational Visioning sessions with AHS faculty, district leaders and community members January & February 2018
Public Forums Held January – June 2018
AHS Building Committee evaluates alternate sites and determines current site is the most viable option March 2018
HMFH Architects presents 8 preliminary ‘massing’ concepts March 2018
AHS Building Committee deemed a renovation-only option unsuitable March 2018
AHS Building Committee selects 4 preliminary designs to further explore April 2018
Preliminary Design Program (PDP) submitted to MSBA April 25, 2018
AHS Building Committee votes Option 3a as Preferred Design Concept June 26, 2018
Arlington submits Preferred Schematic Report (PSR) to MSBA Estimated July 2018
Schematic Design Estimated Fall 2018
Funding the Project (Debt Exclusion Town Election) Estimated Spring 2019
Detailed Design Estimated Spring 2019 – Spring 2020
Phased Construction Begins Estimated Spring 2020
Anticipated Completion Phased Occupancy Between 2022 and 2024