Following is a brief overview of next steps in the project. For more background, view the historic timeline of the project.

DateMilestone
April 2020Construction Phase: Site pre-work begins
November 2020Phased construction begins 
Est. February 2022Phase 1 complete and occupied: Performing Arts and STEAM (Science, Technology, Engineering, Arts & Mathematics) wings
Est. February 2022 – July 2023Phase 2 construction. Demolition of Collomb House; construction of central spine, humanities wing, media center, cafeteria, district administration.
Est. July 2023 – July 2024Phase 3 construction. Demolition of Fusco House and blue gym; construction of gymnasium.
Est. July 2024 – April 2025Phase 4 construction. Demolition of red gym and Downs House, construction of new athletic fields and completion of site work.