Next Steps

Following is a brief overview of next steps in the project. For more background, view the historic timeline of the project or the phased construction diagrams.

Date Milestone
November 2020 – February 2022 Phase 1 construction of the STEAM (Science, Technology, Engineering, Arts and Mathematics) and Performing Arts wings.
March 2022 – January 2024 Phase 2 construction. Partial demolition of old school; construction of central spine, humanities wing, library, cafeteria, learning courtyard, district administration, preschool.
Estimated
November 2023 – December 2024
Phase 3 construction. Partial demolition of old school; construction of gymnasium, black box theater, outdoor amphitheater.
Estimated
January 2025 – September 2025
Phase 4 construction. Remaining demolition of old school; construction of additional athletic fields, completion of site work, connector to Minuteman Bikeway.