Next Steps

Following is a brief overview of next steps in the project. For more background, view the historic timeline of the project or the phased construction diagrams.

DateMilestone
April 2020Construction Phase: Phase 1 site pre-work begins
November 2020 – February 2022Phased construction begins. Phase 1 construction of the STEAM (Science, Technology, Engineering, Arts and Mathematics) and Performing Arts wings.
Estimated February 2022 – September 2023Phase 2 construction. Demolition of Collomb House; construction of central spine, humanities wing, media center, cafeteria, district administration.
Estimated February 2022 – September 2023Phase 3 construction. Demolition of Fusco House and blue gym; construction of gymnasium.
Estimated June 2024 – May 2025Phase 4 construction. Demolition of red gym and Downs House, construction of new athletic fields and completion of site work.