90% Construction Documents, submitted to the MSBA on August 27, 2020
60% Construction Documents, submitted to the MSBA on May 14, 2020
Detailed Design, submitted to the MSBA on January 23, 2020
Schematic Design, approved by MSBA on April 10, 2019
MSBA Schematic Design Board Action Letter, August 2018
Preferred Schematic Report (PSR), submitted to MSBA July 11, 2018
Preliminary Design Program (PDP), submitted to MSBA April 25, 2018
MSBA Owner’s Project Manager Approval Letter, July 2017
MSBA Module One Deliverables for Arlington High School, February 2017
MSBA Follow up Enrollment Letter, January 2017
MSBA Enrollment Letter, November 2016
MSBA Initial Compliance Certification, July 2016
MSBA Eligibility Period Board Action Letter, May 2016
MSBA Deliverables Timeline for Arlington High School, May 2016
Statement of Interest (SOI), April 2015