Geothermal wells removed from project

April 2020

At its March 24 meeting, the Building Committee voted to remove geothermal wells from the project. This decision came after the discovery of unanticipated contaminants during geothermal test well drilling at the Peirce Practice Field in February.

Learn about:
What’s Next:
  • HMFH Architects will make adjustments to the design of the new school to use alternate technology for heating and cooling the new building.
  • In addition, the Building Committee directed the design team to further evaluate additional sustainability features that can be incorporated into the project.
Tell me more:
What happened before this?

Upcoming Events

Recent News

Minuteman Bikeway connection construction

Dec. 11-13, 2024 AHS Bikeway Ramp Connection Work  Connection will open at the completion of Phase 4, Summer 2025  Beginning Wednesday, December 11th, construction activity will take place on the Minuteman Bikeway, adjacent to Arlington High School (AHS) where the...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...