5 At A Glance 5 What’s Happened so far? 5 Detailed Design phase begins

Detailed Design phase begins

November 2019

After the approval of the June debt exclusion vote, the project entered the Detailed Design phase. During this year long phase, the project team will continue to move the project forward and exact details of the design and construction logistics will be developed. The Detailed Design Phase includes three parts: Design Development, Construction Documentation, and Bidding.

As part of the process, a revised project estimate was performed, revealing a gap of $29.5 million between the design development estimate and the approved project budget.

Over the next month, the Building Committee will be discussing both value engineering decisions and design modifications to stay within the approved budget. 

Learn about:
What’s Next:
  • Design Development documents will be submitted to the MSBA in the coming weeks
  • Site pre-work is expected to begin in February 2020 and construction in October 2020.
Tell me more:
What happened before this?

Upcoming Events

Recent News

Minuteman Bikeway connection construction

Dec. 11-13, 2024 AHS Bikeway Ramp Connection Work  Connection will open at the completion of Phase 4, Summer 2025  Beginning Wednesday, December 11th, construction activity will take place on the Minuteman Bikeway, adjacent to Arlington High School (AHS) where the...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...