Phase 2 Schedule Update

May 7, 2023

Phase 2 construction of the new high school is currently underway and includes the central concourse, humanities classroom wing, library, cafeteria, exterior courtyard, District offices and Menotomy Preschool.   

After reviewing the Phase 2 construction schedule, on May 2nd Consigli Construction informed the AHS Building Committee that they will be unable to meet the initial Phase 2 turnover date of September 19, 2023. The revised schedule for turning over all Phase 2 AHS spaces, including the District Administration offices, is now October 11, 2023. AHS students and staff are anticipated to move into the new spaces by the end of October. The delayed schedule will not affect teaching and learning. As previously determined, the Menotomy Preschool wing will be turned over to the district in December 2023 and will open to students in January 2024. 

At the May 2 meeting, the project team reiterated that the Phase 2 schedule has always been the tightest of the four phases. Though the winter was relatively mild, there were numerous steel and concrete work delays due to frequent rain and strong winds. The construction team has been working overtime, including extended hours, Saturdays and holidays the entire phase, but those efforts are not enough to recover the lost work days. There is no additional cost to the Town for the delay in the schedule.

In October 2022, the AHS Building Committee had voted to delay demolition of parts of the old school in order to avoid disruption to students at the beginning of the next two school years. That decision accommodated a normal start of school in the fall of 2023. The demolition delay also accommodates later schedule changes with an anticipated 3 month delay for Phase 3 and Phase 4 respectively. 

Following is the revised schedule for the remainder of the project.

Phase Original completion date Revised completion date
2 September 2023 AHS spaces, District Administration – October 2023


Menotomy Preschool – December 2023
(students occupy after holiday break)

3 September 2024 December 2024
(students occupy after holiday break)
4 April 2025 September 2025
(fields available for start of school)

 

Resources:

Blog: Schedule Update (October 2022)

Upcoming Events

Recent News

Welcome Back Students!

As the new school year gets underway, the following resources will help students, parents and community members access the high school during Phase 3 construction.

Arlington is victim of cybercrime

A Message from Jeff Thielman, Chair of the AHS Building Committee  Arlington Town Manager Jim Feeney announced today that the Town of Arlington and the AHS Building Project were recently victims of cybercrime. I would like to thank Mr. Feeney and the Town for their...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Blog: Phase 3 Preview

Phase 3 construction of the new high school began immediately after the opening of Phase 2 and is anticipated to be complete by February 2025. During this last phase of construction, the athletics wing, outdoor amphitheater, and black box theater will be built. Read...

Connect with us

Sign up to receive updates