Next Steps

Following is a brief overview of next steps in the project. For more background, view the historic timeline of the project or the phased construction diagrams.

DateMilestone
November 2020 – February 2022Phase 1 construction of the STEAM (Science, Technology, Engineering, Arts and Mathematics) and Performing Arts wings.
March 2022 – January 2024Phase 2 construction. Partial demolition of old school; construction of central spine, humanities wing, library, cafeteria, learning courtyard, district administration, preschool.
Estimated
November 2023 – February 2025
Phase 3 construction. Partial demolition of old school; construction of gymnasium, black box theater, outdoor amphitheater.
Estimated
January 2025 – September 2025
Phase 4 construction. Remaining demolition of old school; construction of additional athletic fields, completion of site work, connector to Minuteman Bikeway.

 

Upcoming Events

Recent News

Welcome Back Students!

As the new school year gets underway, the following resources will help students, parents and community members access the high school during Phase 3 construction.

Arlington is victim of cybercrime

A Message from Jeff Thielman, Chair of the AHS Building Committee  Arlington Town Manager Jim Feeney announced today that the Town of Arlington and the AHS Building Project were recently victims of cybercrime. I would like to thank Mr. Feeney and the Town for their...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Blog: Phase 3 Preview

Phase 3 construction of the new high school began immediately after the opening of Phase 2 and is anticipated to be complete by February 2025. During this last phase of construction, the athletics wing, outdoor amphitheater, and black box theater will be built. Read...