Phase 2 Schedule Update

Updates

Phase 2 construction of the new high school is currently underway and includes the central concourse, humanities classroom wing, library, cafeteria, exterior courtyard, District offices and Menotomy Preschool.    After reviewing the Phase 2 construction schedule, on May 2nd Consigli Construction informed the AHS Building Committee that they will be unable to meet the initial Phase 2 turnover date of …

Topping Off beam placed - December 2022

Phase 2 ‘Topping Off’ beam placed

Updates

The ‘Topping Off’ beam of Phase 2 – one of the final beams installed and the one that the AHS Senior class signed – was lifted into place on December 29th. The white beam is topped with a ceremonial evergreen tree and flag and is visible from the Mill Brook Street entrance. The steel framing of Phase 2 is nearly …

AHS Senior Class Signs Beam

Updates

Last week, the AHS senior class signed the final beam that will be placed in the Phase 2 wings. The beam will be lifted into place within the next few weeks and visible from Mill Brook Drive.

Construction Timeline and Grade Comparison

Updates

Wondering what parts of the building project will be in process or completed when your child is a student at AHS? This updated K-12 chart will help you. Find the current grade of your student in the left column. Each grade’s row (from left to right), indicates what will be happening from their Freshman to Senior years.

Blog: Schedule Update

Updates

In order to avoid disruption to students at the beginning of the next two school years, the AHS Building Committee and School Committee recently voted to delay demolition of parts of the old school. This decision accommodates the start of school before the Phase 2 buildings are available at the end of September 2023. As a result, there will be …

Updated Photo Gallery and Progress Video

Updates

Phase 2 construction is well underway and the landscaping on the front green is nearly complete, with new sidewalks, trees, benches and plantings. Demolition of parts of the old building continue and site preparation for the next phase of construction will begin later this month. Watch the June progress video on our Vimeo channel View the updated construction photo gallery

April 30, Tours of new wings

Updates

The public is invited to tour the new wings of the high school on Saturday April 30 between 10am and 2pm. RSVP is encouraged, but not required (https://tinyurl.com/AHSTour22). Self-guided tours will begin and end at the Mass. Ave. lobby and will only include the new wings. Attendees are advised to park near the Mass. Ave. entrance. The rear entrance on …

Photo Gallery of the New Wings

Updates

This photo gallery gives you an inside look at the new STEAM (Science, Technology, Engineering, Arts & Mathematics) and Performing Arts wings. We hope to offer tours of the building later this spring when the Auditorium is complete. We will post any tour information on this site. Take a virtual tour of the Phase 1 wings with the AHS Principal. …