The AHS Building Committee and town officials recently celebrated a significant milestone in the construction of the new Arlington High School. On the morning...
News Updates
January Forum Materials
The much anticipated first wings of the new high school will open at the end of February and the next phase of construction will begin soon thereafter. A lot...
New Interior Photos!
With only five weeks to go until the new wings open, things are coming together very quickly. We've updated our construction progress photo gallery and are...
Phase 2 Preparation
The project team was busy over winter break moving the library and cafeteria to their temporary homes during Phase 2 of construction. The library moved to Old...
January eBulletin
The new Performing Arts and STEAM (Science, Technology, Engineering, Arts & Mathematics) classroom spaces are expected to open February 28 and the...
360° Interior Photos
These 360° interior photos were taken in late November and show the progress of a number of interior spaces, including science classrooms. [x_share...
Jan. 25 Virtual Community Forum
Forum access link The first wings of the new high school will open after February break and Phase 2 of construction will begin soon thereafter. A second...
Dec. Abutter Meeting Materials
Starting March 2022 demolition of the old school and new construction will begin at the back of the school. There will be increased activity in the rear of...
Dec. Forum Materials
The first wings of the new high school will open in a few months and the next phase of construction will begin soon thereafter. To prepare for this...
Updated Photo Gallery
With the first wings set to open in February 2022, we've updated our construction photo gallery to show how quickly things are coming together. Check the site...
Dec. 15 Virtual Community Forum
Forum access link The first wings of the new high school will open in a few months and the next phase of construction will begin soon thereafter. To prepare...
Recent News
Connect with us
Sign up to receive updates