Site work begins, project on budget

May 2020

Site work to prepare for Phase 1 construction began in April. Work performed during this period includes site excavation, new sewer and utility lines, new parking lots, and pouring foundations for the STEAM (Science, Technology, Engineering, Arts & Mathematics) classroom wing and the Performing Arts wing that will be built in front of the current school, completely separate from the existing school.

In addition, in the Mass. School Building Authority (MSBA) process, a new cost estimate is performed when 60% of the construction documents have been completed. Consigli, the project’s construction manager, recently completed the 60% Construction Document estimate that showed that the project is on budget. 

Learn about:
What’s Next:
  • The final cost estimate is anticipated at the end of the summer when 90% of the construction documents are complete.
  • Steel construction of the new wings is scheduled to begin in November.
Tell me more:
What happened before this?

Upcoming Events

Recent News

Phase 4 Site Impacts

Phase 4, the final phase of the Arlington High School Building project, includes construction of two additional synthetic turf multi-sport fields and a Minuteman Bikeway connector. This final phase is anticipated to be completed by September 2025.

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...