Schedule Update

OCTOBER 2022

In order to avoid disruption to students at the beginning of the next two school years, the AHS Building Committee and School Committee voted to delay demolition of parts of the old school. 

This decision accommodates the start of school before the Phase 2 buildings are available at the end of September 2023. As a result, there will be an overall delay in the completion of the new school buildings by three months. Additional costs will be covered by project contingency funds.

LEARN ABOUT:
WHAT’S NEXT:
  • Phase 2 construction is underway and is estimated to be complete September 2023.
  • Phase 2 spaces include the central spine, library, humanities classroom wing, cafeteria, district administration offices and Menotomy Preschool.
TELL ME MORE:
WHAT HAPPENED BEFORE THIS?

 

Upcoming Events

Recent News

Phase 4 Site Impacts

Phase 4, the final phase of the Arlington High School Building project, includes construction of two additional synthetic turf multi-sport fields and a Minuteman Bikeway connector. This final phase is anticipated to be completed by September 2025.

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...