OCTOBER 2022
In order to avoid disruption to students at the beginning of the next two school years, the AHS Building Committee and School Committee voted to delay demolition of parts of the old school.
This decision accommodates the start of school before the Phase 2 buildings are available at the end of September 2023. As a result, there will be an overall delay in the completion of the new school buildings by three months. Additional costs will be covered by project contingency funds.
LEARN ABOUT:
WHAT’S NEXT:
- Phase 2 construction is underway and is estimated to be complete September 2023.
- Phase 2 spaces include the central spine, library, humanities classroom wing, cafeteria, district administration offices and Menotomy Preschool.
TELL ME MORE:
- Construction timeline
- Watch the Consigli Phase 2 Sequence Video for more details.
- The Construction Timeline and Grade Comparison chart outlines what parts of the building project will be in process or completed over the next few years.
- Construction Photo Gallery
WHAT HAPPENED BEFORE THIS?
- April 2022 – Auditorium open, Public Tours
- February 2022 – Phase 1 Wings Open
- June 2021 – Phase 1 Schedule Update
- see all