5 Featured 5 Phase 3 Schedule Update

Phase 3 Schedule Update

March 10, 2024

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor amphitheater. The new wing will also include Arlington Community Education office space and program spaces for the Special Education LABBB Collaborative program that serves Lexington, Arlington, Burlington, Bedford, Belmont and Watertown.

At the AHS Building Committee meeting on February 6, the project team informed the Committee that the Phase 3 schedule will shift from the end of December 2024 to February 2025. Due to the slight delay of the Phase 2 opening, the beginning of Phase 3 was delayed and the project team is unable to make up the time lost. The new timeline avoids disruption to students by moving into the new spaces over February vacation.

With the opening of Phase 2 in November 2023, three-quarters of the new high school is now complete. The Phase 3 schedule adjustment does not impact teaching and learning and there is no cost associated with the schedule change. Winter athletics programs will continue to use the current spaces until Phase 3 is completed.

The estimated completion date for Phase 4 remains as September 2025. Phase 4 entails final site work and the construction of two additional multi-use, synthetic turf athletic fields, plus landscaping and a connection to the Minuteman Bikeway. 

Resources:

 

Upcoming Events

Recent News

Minuteman Bikeway connection construction

Dec. 11-13, 2024 AHS Bikeway Ramp Connection Work  Connection will open at the completion of Phase 4, Summer 2025  Beginning Wednesday, December 11th, construction activity will take place on the Minuteman Bikeway, adjacent to Arlington High School (AHS) where the...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...