5 News Updates 5 Blog: Schedule Update: Phase 2

Blog: Schedule Update: Phase 2

September 15, 2023

Phase 2 Buildings Scheduled to Open to Students in early November

Phase 2 construction of the new high school is nearly complete and includes the Humanities Classroom Wing, Student Center (aka central spine), Library, Cafeteria, Exterior Learning Courtyard, District Offices and Menotomy Preschool.

After careful review of the Phase 2 schedule, the project team determined that the planned turnover date of October 11, 2023 was no longer feasible. At the September 5th AHS Building Committee meeting, the project team informed the Committee that the new turnover date will be October 30, 2023. As previously determined, Menotomy Preschool will be turned over to the district in December 2023 and will open to students in January 2024.

Read our Blog: Schedule Update: Phase 2 for more details.

Upcoming Events

Recent News

Phase 3 Photo Gallery

This photo gallery gives you an inside look at the new AHS Athletics wing and other Phase 3 spaces. Click on any image to view a slideshow.

Phase 3 is Open!

With the opening of Phase 3, construction of new high school buildings is completed. Only a short final phase of site work will follow. The new Athletics wing and Black Box Theater opened on February 24. Additional parts of Phase 3 include an outdoor amphitheater,...

Phase 4 Site Impacts

Phase 4, the final phase of the Arlington High School Building project, includes construction of two additional synthetic turf multi-sport fields and a Minuteman Bikeway connector. This final phase is anticipated to be completed by September 2025.

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...