Phase 2 construction is well underway. Foundation work for the new Humanities and Preschool wing is nearly complete and steel beams will be raised later this month. Landscaping of the front green is now complete.
- View the latest progress video on our Vimeo channel
- Visit our updated construction photo gallery
Phase 2 of construction, estimated to conclude in September 2023, includes construction of the central spine, forum stairs, cafeteria, library, humanities classroom wing, learning courtyard, and the District Admin/Preschool wing. The new school is anticipated to be complete in 2024, followed by a year of site work.