The first wings of the new high school will open in a few months and the next phase of construction will begin soon thereafter. To prepare for this February/March 2022 transition, the Building Committee is hosting two community forums on December 15 and January 25. Below are the supporting materials from the December forum.

View the supporting materials:

Check back often for project updates.

Recent News

Photo Gallery

View a complete overview of the new school in this comprehensive photo gallery.

AHS Completion Celebration

On October 25, 2025 the Town of Arlington officially celebrated the completion of the new Arlington High School with a morning ribbon cutting ceremony and afternoon Community Open House.  We appreciate the support from our local and state officials, the Arlington...

Project Milestones & Statistics

As we celebrate the completion of the new Arlington High School, we reflect on the overall project. These milestones and statistics represent over nine years of work by the AHS Building Committee and project partners. Click on any image to expand.

Phase 4 Photo Gallery

This photo gallery highlights the final features of the newly completed high school. Click on any image to view a slideshow.

AHS LEED Case Study

Integrating sustainability into the new high school was a collaborative process from the very beginning. The design team worked with building users to address site energy and water use with sustainability in mind. The new school's design helps Arlington make...