5 News Updates 5 December Estimate and Decisions Update

December Estimate and Decisions Update

December 13, 2019

The AHS Building Committee would again like to update the community on the building project status. In November, after receiving the Design Development estimate, the Committee requested the design and construction team to further clarify and review the project estimate. This process has resulted in a final Design Development estimate that shows a gap of $24.7 million between estimate and budget, a decrease of ~$5 million since November. Much of the remaining gap is attributable to the rapidly changing construction market and the number of large, competing projects underway.

The Building Committee continues its work to align the project with the approved budget through value engineering, design modifications, and changes in scope. During meetings on December 3rd, 9th, and 10th, the group discussed a variety of ways to close the gap, while maintaining the education program and functionality, building quality, and sustainability. Also considered was the ability to list some items as alternates, which would allow them to be included later in the project if the budget allows.

One of the largest items being discussed is reducing the number of geothermal wells while still maintaining the sustainability goals of an all-electric and carbon-neutral building. Other large items include lighting and artificial turf for the new athletic fields, bike path connection, eastside pedestrian stairs and ramp, and modified materials and design. The inclusion of some of these components may mean the potential exclusion of others. Though considered, changes to project phasing was discarded because of student impact and negligible savings. 

The Building Committee will meet next on December 17th to further discuss the project team’s suggestions with the goal of making final decisions on aligning the project with the budget. A second meeting is scheduled on December 18th in case it is needed. To maintain the project timeline it is important to finalize the project scope as soon as possible. 

As the AHS Building Project continues to move forward, the Committee remains committed to both fiscal responsibility and building an educationally exceptional facility that will serve our town for generations.

Learn More

Upcoming Events

Recent News

Minuteman Bikeway connection construction

Dec. 11-13, 2024 AHS Bikeway Ramp Connection Work  Connection will open at the completion of Phase 4, Summer 2025  Beginning Wednesday, December 11th, construction activity will take place on the Minuteman Bikeway, adjacent to Arlington High School (AHS) where the...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Connect with us

Sign up to receive updates