5 News Updates 5 Next Community Forum 10/30

Next Community Forum 10/30

October 17, 2019

The AHS Building Project has moved into the Design Development phase and project partners have been busy over the summer. Learn more about the project’s progress at the next Community Forum on October 30th, from 7-8:30pm at Town Hall. 

Topics covered will include:

  • Project overview and process going forward, including the next phase of Estimating and Value Engineering
  • HMFH Architects design update – facade, interior, athletic fields
  • Consigli Construction – timeline, phasing plans, student impact

The forum will answer questions such as: “What updates have been made to the design?”, “What buildings will be completed when my 6th/7th/8th/etc. grader is at AHS?” and “What effect will construction have on students?”

During the Design Development phase (summer 2019 – summer 2020), all aspects of the design for the new school will be finalized. Current plans are to begin construction pre-work in March 2020 and construction in October 2020. The first building is expected to be open to students in January 2022, and the school fully constructed in 2024 (followed by one year of site work).

Upcoming Events

Recent News

Phase 3 Photo Gallery

This photo gallery gives you an inside look at the new AHS Athletics wing and other Phase 3 spaces. Click on any image to view a slideshow.

Phase 3 is Open!

With the opening of Phase 3, construction of new high school buildings is completed. Only a short final phase of site work will follow. The new Athletics wing and Black Box Theater opened on February 24. Additional parts of Phase 3 include an outdoor amphitheater,...

Phase 4 Site Impacts

Phase 4, the final phase of the Arlington High School Building project, includes construction of two additional synthetic turf multi-sport fields and a Minuteman Bikeway connector. This final phase is anticipated to be completed by September 2025.

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Connect with us

Sign up to receive updates