5 News Updates 5 Community Forum & Tours

Community Forum & Tours

May 15, 2019

To help residents learn more about the AHS Building Project in advance of the June 11 town-wide debt exclusion vote to pay for a new school, the AHS Building Committee has scheduled the following events:

May 21 Community Forum
7pm, Town Hall
AHS Building Committee leaders will present details on the educational vision, design concept and cost. Residents are invited to ask questions and provide feedback.

Tours of the High School
Tours will last approximately 45 minutes and will be followed by a brief informational Q&A.

  • May 23, 7pm – tours will depart between 7-7:20pm
  • June 2, 1pm – tours will depart between 1-1:20pm

For more information on the proposed project design, view a virtual fly-through video.

The state approved Arlington’s Schematic Design in April and will contribute an estimated $86M to the $291M project. If the June debt exclusion is approved, a final year of design work would start this summer. Construction could begin as early as summer 2020 with the first buildings available to students in early 2022.

Upcoming Events

Recent News

Minuteman Bikeway connection construction

Dec. 11-13, 2024 AHS Bikeway Ramp Connection Work  Connection will open at the completion of Phase 4, Summer 2025  Beginning Wednesday, December 11th, construction activity will take place on the Minuteman Bikeway, adjacent to Arlington High School (AHS) where the...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Connect with us

Sign up to receive updates