5 News Updates 5 Blog: High School Benchmarks: We are not alone

Blog: High School Benchmarks: We are not alone

January 14, 2019

Arlington, Belmont, Waltham, Saugus and Somerville are five High School building projects navigating through similar challenges–dense suburbs with somewhat comparably scaled projects being undertaken generally within the same timeframe. While there are similarities between the projects, none of these projects (or other projects in the state) are comparable in complexity to Arlington High School. Read our latest Pondering Blog ‘High School Benchmarks: We are not alone‘ to learn more.

2/13/19 Note: The figures used in this blog are based on Preferred Schematic Report estimates. At the PSR stage, Arlington’s estimate was $308M. At the end of Schematic Design, Arlington’s project budget is now $291M. We are in the process of updating this benchmark comparison to compare Schematic Design costs with other projects.

Upcoming Events

Recent News

Welcome Back Students!

As the new school year gets underway, the following resources will help students, parents and community members access the high school during Phase 3 construction.

Arlington is victim of cybercrime

A Message from Jeff Thielman, Chair of the AHS Building Committee  Arlington Town Manager Jim Feeney announced today that the Town of Arlington and the AHS Building Project were recently victims of cybercrime. I would like to thank Mr. Feeney and the Town for their...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Blog: Phase 3 Preview

Phase 3 construction of the new high school began immediately after the opening of Phase 2 and is anticipated to be complete by February 2025. During this last phase of construction, the athletics wing, outdoor amphitheater, and black box theater will be built. Read...