Sustainability Update: Mechanical System Changes
If you’ve been following the Design Development process, you know that the Building Committee recently completed the difficult task of trimming...
Budget Adjustments Explained
In December 2019, the AHS Building Committee made a number of changes to the project design to bring the estimated cost in line with the project...
Summary of Project Adjustments
The project entered the Design Development phase in June 2019. During this phase, the design becomes more detailed and a new cost estimate is done....
What is Value Engineering?
Value engineering is the process of comparing alternatives and their associated costs, and making choices to keep the project within budget, without...
Detailed Design Overview
This blog post provides an overview of the Detailed Design Phase of the High School Building Project. On June 11, 2019, Arlington voters...
Student Impact During Construction
Safety of students and staff, and minimizing disruption are the project’s highest priorities. The proposed school will be built in multiple phases...
A Teacher’s Perspective: AHS Science Classrooms
Shannon Knuth has been a science teacher at AHS since 2015. While I have lived in Arlington for 10 years, my first experience with the AHS building...
A Teacher’s Perspective: AHS’ Limitations
Kent Werst has been a mathematics teacher at AHS since 2005. The current Arlington High School has many deficiencies. I am going to discuss three...
The Future: Enrollment and Design Flexibility
Arlington Public Schools’ student population is increasing - with about 200 new students added just this past year - and the high school is no...
Sustainability for the New AHS – An Update
Sustainability is integral to the new high school design and over the past year, the AHS Building Committee has made substantial progress on...