5 Documents 5 Document Archive

Document Archive

This is a repository of miscellaneous documents from the building project.  Refer to the Mass. School Building Authority page for official submissions.

Presentations & Drawings

AHS Phase 3 Traffic Plan, August 2024

AHS Construction Phasing Diagram, March 2024

AHS Phase 3 Traffic Plan, January 2024

Fall 2023 Traffic/Arrival Map, November 2023

Construction Phasing Diagram, November 2023

Fall 2023 Traffic/Arrival Map, August 2023

Construction Phasing Diagram, October 2022

AHS Construction Timeline and Grade Comparison, October 2022

Fall 2022 Traffic/Arrival Map, August 2022

Project Update: Opening of New Wings & What’s Next #2(Forum Presentation), January 2022

Project Update: Opening of New Wings & What’s Next (Forum Presentation), December 2021

Abutter Meeting presentation and replay, December 2021

Winter/Spring 2022 Traffic/Arrival Map, November 2021

AHS Construction Timeline and Grade Comparison, September 2021

Fall/Winter 2021 Traffic/Arrival Map, August 2021

Construction Phasing Diagram, April 2021

AHS Construction Timeline and Grade Comparison, September 2020

Construction Update: Site work begins soon (Forum Presentation), February 2020

Project Update: Site work begins soon (Forum Presentation), February 2020

Construction Site Maps, February 2020

Project Update (Forum Presentation), October 2019

AHS Construction Timeline and Grade Comparison, October 2019

HMFH Design Update, October 2019

HMFH Design Update, September 2019

Construction Phasing Diagram, September 2019

HMFH Design Update, August 2019

Abutters Meeting Presentation, July 2019

Consigli Overview Presentation (Construction Manager), June 2019

Project Update (Forum Presentation), May 2019

Town Meeting – Report, Presentation,  ACMi replay, April 2019

Presentation to Select Board, April 2019

Open Space Overview, Feb. 2019

HMFH Design Update, Feb. 2019

HMFH Exterior Facade Update, Jan. 2019

Community Forum – Project Update and Costs, Jan. 2019

HMFH Project Update, Jan. 2019

HMFH Design Update, Dec. 2018

Construction Manager at Risk Overview, Dec. 2018

HMFH Exterior Facade Update, Dec. 2018

Schematic Design Update (exterior facade, site plan, and more), Nov. 2018

Community Forum – Project Overview and Update , Nov. 2018

HMFH Design Concept Update (floor plans, exterior concepts), Nov. 2018

HMFH Design Concept Update (historic element reuse, central spine), Nov. 2018

HMFH Initial Exterior Design Concepts, Oct. 2018

HMFH Front Green Update, Oct. 2018

Community Forum – Project, Design, Cost Updates, Sept. 2018

Preferred Design Concept Images, June 2018

Preferred Design Concept Preliminary Construction Phasing, June 2018

AHS Space Summary (updated), June 2018

Updated Design Concepts (HMFH Presentation), June 2018

AHS Preferred Design Alternatives, May 2018

Preliminary Evaluation of Alternatives (excerpt from Preliminary Design Program), April 2018

Original 8 Preliminary Design Alternatives, April 2018

Communication

Student Quick Guide, August 2024

Phase 3 FAQ, August 2024

Student Quick Guide, August 2023

Phase 2 FAQ, August 2023

Student Quick Guide, January 2022

Phase 1/Phase 2 Transition FAQ, December 2021

Student Quick Guide, August 2021

Student Quick Guide, September 2020

Project Overview, September 2019

Project Overview, April 2019

School Committee Value Engineering letter to AHS Building Committee, Jan. 2019

School Committee letter to AHS Building Committee, January 2019

A message from the AHS Building Committee Chair:  Moving forward together, September 2018

AHS Building Committee Leadership Editorial: The AHS Project – Progress Made and Decisions Ahead, September 2018

Environmental & Sustainability

LEED Scoresheet (submitted with 90% Construction Documents), August 2020

Accelerate Perform Program Targets, Nov. 2018

Preliminary Sustainability Evaluation Matrix, June 2018

Education-Related Documents

Guiding Principles Evaluation Evaluation Chart and Supporting Diagrams, June 2018

AHS Educational Program (updated), June 2018 (Redacted)

Adjacency Diagram, March 2018

Educational Visioning Report, March 29, 2018 (Redacted)

Request for Proposals

Upcoming Events

Recent News

Welcome Back Students!

As the new school year gets underway, the following resources will help students, parents and community members access the high school during Phase 3 construction.

Arlington is victim of cybercrime

A Message from Jeff Thielman, Chair of the AHS Building Committee  Arlington Town Manager Jim Feeney announced today that the Town of Arlington and the AHS Building Project were recently victims of cybercrime. I would like to thank Mr. Feeney and the Town for their...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Blog: Phase 3 Preview

Phase 3 construction of the new high school began immediately after the opening of Phase 2 and is anticipated to be complete by February 2025. During this last phase of construction, the athletics wing, outdoor amphitheater, and black box theater will be built. Read...

Connect with us

Sign up to receive updates