5 Blog Post 5 Highlights of Phase 2 Spaces

Highlights of Phase 2 Spaces

November 8, 2023

The largest and most complex of the four phases, Phase 2 features a 44 classroom Humanities wing, a 600 seat Cafeteria, a two-story Library, exterior Learning Courtyard, School District offices, and the School Committee room. Also included is Menotomy Preschool, which is anticipated to open to students in early January 2024.

Three-quarters of the building is now complete and all the new academic wings in addition to the performing arts wings are all in use – only the athletic wing remains!

The following spaces are now in use by students and staff. View the full photo gallery.

Student Center

Phase 2 fulfills the vision of the new Student Center which has been designed as the core of the school. This combination of collaborative, learning and social spaces is situated at the intersection of the four wings of the new school. The Student Center features the Mass. Ave. and field entrance lobbies, forum stairs, learning center, cafeteria, student cafe/store, and outdoor learning courtyard. Directly above, spaces include the library, discourse lab, and new immersion lab.

Library

Centrally located within the Student Center and adjacent to the STEAM (Science, Technology, Engineering, Arts and Mathematics) and Humanities wings, the Library is envisioned as the heart of the school, and provides a flexible and inclusive space for academics.

Humanities Wing

Forty-four 850 – 950 sf classrooms for World Language, English Language Arts, History and Social Studies. Two 1,200 sf FACS (Family and Consumer Science) classrooms. With the completion of Phase 2, all primary AHS classroom spaces are now located in the new buildings.

Forum Stairs

Connecting the Student Center, cafeteria and field entry of the school, the forum stairs provide a gathering and collaboration space for students and staff at all times of day. The stairs provide a dual purpose: one side is a staircase with access to the cafeteria; the other has high risers for sitting and convening.

Cafeteria

Adjacent to the forum stairs and outdoor learning courtyard, the new cafeteria has seating for ~600 students, upgraded food stations, and an outdoor courtyard where students can eat.

Sustainability

The new school significantly contributes to the Town’s net-zero sustainability goals. As one of the first all-electric high schools in Massachusetts, the project is working towards receiving LEED Platinum certification. From air-source heat pumps, lightwells bringing daylight deep into the building and a more energy efficient building envelope, the new school minimizes its carbon footprint on the town.

Outdoor Learning Courtyard

The outdoor learning courtyard is an outdoor classroom, gathering and breakout space for students. The courtyard also features an Envirogarden designed for gardening, engineering, and biology experiments. The courtyard is still under construction and will be complete in 2024.

Lifeskills Cafe

The student-run school store and cafe provides hands-on learning activities for students (work transition, career readiness, and FACS).

Community Hub and Resource

All parts of the school – including the Auditorium, Library, Discourse Lab and the future Gymnasium – are easily accessed for public events and community use. In addition, Arlington Community Education uses the entire building for classes from September through June. The flexible building layout allows for closure of spaces not being used during non-school hours.

District Administration Offices

District administration now has dedicated office space separate from the high school. This section of the building also includes the new district Welcome Center and the School Committee Room.

Menotomy Preschool

The Town’s inclusion-based preschool has a separate and secure entry, age-appropriate interior classrooms and a dedicated exterior playspace. The new school features 8 classrooms, a two-story multi-purpose room that functions as a gymnasium and a space where physical and occupational therapy services can be provided, and 2 daycare rooms for Arlington Public Schools staff.

Project timeline

Since the new school is being built on the same site as the old school, the complex project encompasses four phases of construction, with completion of the entire project in 2025.

Phase Construction Where do students attend school? When?
1 STEAM & Performing Arts wings Old high school Completed
February 2022
2 Humanities wing, Student Center, Cafeteria,
Media Center, Preschool, District offices
In new STEAM & Performing Arts wings and part of old high school Completed
December 2023
3 Athletics wing, black box theater,
outdoor amphitheater
In new school plus Red gym November 2023 to February 2025
4 Finish athletic fields and site work In new school February 2025 to September 2025

Resources:

Updated 6/3/24

Upcoming Events

Recent News

Welcome Back Students!

As the new school year gets underway, the following resources will help students, parents and community members access the high school during Phase 3 construction.

Arlington is victim of cybercrime

A Message from Jeff Thielman, Chair of the AHS Building Committee  Arlington Town Manager Jim Feeney announced today that the Town of Arlington and the AHS Building Project were recently victims of cybercrime. I would like to thank Mr. Feeney and the Town for their...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Blog: Phase 3 Preview

Phase 3 construction of the new high school began immediately after the opening of Phase 2 and is anticipated to be complete by February 2025. During this last phase of construction, the athletics wing, outdoor amphitheater, and black box theater will be built. Read...