APRIL 2022
With the opening of the Auditorium, the public was invited to tour the new wings on April 30.
LEARN ABOUT:
WHAT’S NEXT:
- Phase 2 of the project began in March and entails demolition of part of the old school and construction of the library, central spine and a new wing that includes humanities, district offices and Menotomy Preschool.
TELL ME MORE:
- Demolition of Fusco House is anticipated to take place from March to June, and the newly constructed Phase 2 buildings are expected to open September 2023. Watch the Consigli Phase 2 Sequence Video for more details.
- The Construction Timeline and Grade Comparison chart outlines what parts of the building project will be in process or completed over the next few years.
- Construction Photo Gallery
WHAT HAPPENED BEFORE THIS?
- February 2022 – Phase 1 Wings Open
- June 2021 – Phase 1 Schedule Update
- December 2020 – Cost reduced, items added back, GMP signed
- see all