5 At A Glance 5 What’s Happened so far? 5 Phase 1 Wings Open

Phase 1 Wings Open

FEBRUARY 2022

Mass Ave entrance

The STEAM (Science, Technology, Engineering, Arts and Mathematics) and Performing Arts wings opened February 28, 2022, and the Auditorium is anticipated to open in early April. 

LEARN ABOUT:
WHAT’S NEXT:
  • Completion of the Auditorium (install finishings, seats, stage rigging, etc.).
  • Due to the delayed opening of the Auditorium and out of an abundance of caution, the school has opted to rent the Mosesian Center for the Arts in Watertown for the spring musical since the auditorium opening date and the performance dates are so close together.
  • Phase 2 of the project is now underway and entails demolition of part of the old school and construction of a new wing that includes Humanities, District offices and Menotomy Preschool. 
  • We hope to offer parents and community members tours of the new wings after the Auditorium opens. Tour information will be posted on this site.
TELL ME MORE:
WHAT HAPPENED BEFORE THIS?

Upcoming Events

Recent News

Welcome Back Students!

As the new school year gets underway, the following resources will help students, parents and community members access the high school during Phase 3 construction.

Arlington is victim of cybercrime

A Message from Jeff Thielman, Chair of the AHS Building Committee  Arlington Town Manager Jim Feeney announced today that the Town of Arlington and the AHS Building Project were recently victims of cybercrime. I would like to thank Mr. Feeney and the Town for their...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Blog: Phase 3 Preview

Phase 3 construction of the new high school began immediately after the opening of Phase 2 and is anticipated to be complete by February 2025. During this last phase of construction, the athletics wing, outdoor amphitheater, and black box theater will be built. Read...