5 News Updates 5 Upcoming Design Forums

Upcoming Design Forums

September 12, 2018

The AHS Building Project has now entered the Schematic Design phase and the community is invited to attend a series of Fall/Winter public forums to provide feedback on multiple aspects of the future building’s design.

At each forum, the AHS Building Committee, Skanska and HMFH Architects will update the community, present concepts, answer questions and gather feedback. Topics to be covered include site, exterior facade, and interior layout and features.  

Forums will be held at Town Hall from 7-9pm on:

  • September 24
  • October 24 (Canceled)
  • November 27
  • January/February TBD

The September forum will focus on site definition; exploring possibilities for the front green, traffic flow, entrances, location of school, outdoor learning areas, landscaping, and more. Later forums will focus on the look and feel of the exterior facade as well as interior layout and spaces. Specific forum topics may be added as the design evolves and discussions continue.

During the Schematic Design phase, HMFH Architects will take the preliminary massing diagrams and create a refined design that will establish the look and feel of the building and site. The end result will be a building and site design with enough detail to establish scope, budget and schedule for the new Arlington High School. The AHS Building Committee will be evaluating all possibilities, aiming to maintain educational and community priorities while minimizing cost.

Upcoming Events

Recent News

Welcome Back Students!

As the new school year gets underway, the following resources will help students, parents and community members access the high school during Phase 3 construction.

Arlington is victim of cybercrime

A Message from Jeff Thielman, Chair of the AHS Building Committee  Arlington Town Manager Jim Feeney announced today that the Town of Arlington and the AHS Building Project were recently victims of cybercrime. I would like to thank Mr. Feeney and the Town for their...

Phase 3 Schedule Update

Phase 3 construction of the new high school is currently underway. This phase includes construction of the Athletic wing with a 16,000 square foot gymnasium and two alternate Physical Education spaces, a Black Box theater for performing arts classes and an outdoor...

Virtual Tour of Phase 2 Spaces

Phase 2 of the new high school opened to students in November 2023. Principal Matthew Janger gives a virtual tour of the Phase 2 spaces including the Student Center, Library, Cafeteria, Forum Stairs and Humanities wing. AHS Phase 2 Virtual Tour - January 2024 from...

Phase 2 is Open!

The new Humanities wing and Student Center opened on November 8. Additional parts of Phase 2 include the district administration offices and Menotomy Preschool (which will open to students in early 2024). Communication: Press Release Superintendent's Update Message...

Blog: Phase 3 Preview

Phase 3 construction of the new high school began immediately after the opening of Phase 2 and is anticipated to be complete by February 2025. During this last phase of construction, the athletics wing, outdoor amphitheater, and black box theater will be built. Read...